Nuclear Regulatory Commission (NRC)

The D.C. Circuit ordered NRC to resume processing of DOE's pending license application to store nuclear waste at Yucca Mountain. The Nuclear Waste Policy Act requires NRC to issue a final…

The D.C. Circuit held that NRC's transfer of authority to New Jersey over nuclear materials within the state was arbitrary and capricious. The NRC may transfer regulatory authority over…

The Second Circuit affirmed in part and vacated in part a lower court's grant of summary judgment in favor of the NRC in a case challenging its grant of an exemption to the Indian Point…

The Third Circuit denied environmental groups' petition for review of an NRC decision granting a license renewal for the Oyster Creek Nuclear Generating Station. The groups, who intervened…

The Ninth Circuit, in a case concerning the NRC's approval of a proposed interim spent fuel storage installation at the Diablo Canyon Power Plant, held that the NRC's refusal to…

The D.C. Circuit vacated an NRC decision in which it refused to consider the value of a company's "goodwill" in determining whether the company was exempt from certain financial…

The D.C. Circuit granted a petition challenging the NRC's transfer of regulatory authority over nuclear material to the state of New Jersey. Before transferring authority to a state, the…

The Ninth Circuit denied a petition for review of the NRC's refusal to include the threat of air attacks in its revised "design basis threat" rule, initially promulgated to protect…

The First Circuit denied Massachusetts' petition for review of a Nuclear Regulatory Commission (NRC) order denying its request to participate directly in a re-licensing proceeding of two…

The court upholds a Nuclear Regulatory Commission (NRC) decision denying an interest group's request to intervene in a nuclear power plant's license renewal proceeding. The court first…