Appeal of Northern Pass Transmission, LLC

ELR Citation: 49 ELR 20121
No(s). 2018-0468 (N.H. Jul 19, 2019)

A state high court upheld the New Hampshire Site Evaluation Committee's denial of a utility company's application for siting, construction, and operation of a high-voltage transmission line to carry electricity from Canada into New England. The company argued the committee failed to consider all rel...